Building permit in Colombia: requirements, procedure and validity

Updated November 5, 2026 By Civil Engineer Daniel Horacio Osorio Conde, Grupo D&H y Nacional de Terrenos

Building a house, expanding a floor, or erecting a business premises in Colombia requires a building permit. This permit confirms that your project complies with the municipality's land-use plan and the NSR-10 seismic resistance standard. This guide explains what it is, who issues it, what documents are required, how long it takes, and how to avoid the most common errors that delay the process, based on Decree 1077 of 2015 from the Ministry of Housing.

Write to us on WhatsApp Call: 310 277 8583

What is a building permit?

Law 388 of 1997 and Law 810 of 2003 require a license to urbanize, parcel, subdivide, or divide properties and to construct or demolish buildings. Decree 1077 of 2015 (Single Regulatory Decree for the Housing, City, and Territory Sector) defines five types of urban development licenses:

License classWhat is it for?
UrbanizationCreate public and private spaces, roads and networks on urban or expansion land
ParcellingDividing and providing infrastructure to properties in rural and suburban areas
SubdivisionTo divide a property into lots, in urban, rural or expansion areas
ConstructionTo erect, expand, modify, reinforce or demolish buildings
Intervention and occupation of public spaceWorks on platforms, squares, parks and networks in public space

This guide focuses on the building permit. If you are going to divide a plot of land, read urbanizing and subdividing: licenses and transfers.

Types of building permits

ModeWhen to use
New constructionBuilding on an empty lot or on one where everything has been demolished
ExtensionIncrease the built area, for example by adding a floor
AdequacyChanging the use of a building without altering its structure
ModificationVary the architectural or structural design without increasing the area.
RestorationRecovering properties of cultural interest
Structural reinforcementAdapting a building to the NSR-10
DemolitionTo demolish a building, either partially or completely
ReconstructionTo rebuild a building affected by an event such as an earthquake
EnclosureTo permanently close a property

Who issues the license

In cities with urban planning offices, the procedure is carried out before a urban curator, a private individual performing a public function. In other municipalities, this is done by the Planning Secretariat or Office. The curator or the secretariat verifies that the project complies with the POT, PBOT or EOT (see POT, PBOT and EOT: differences) and the NSR-10.

Documents that are usually requested

Decree 1077 of 2015 and the Ministry of Housing Resolution adopting the national standardized form establish the requirements. Generally, the following are submitted:

  1. Completed national single form.
  2. Certificate of tradition and freedom of the property, with recent issuance.
  3. Applicant's identity document or certificate of existence and representation if it is a company, and power of attorney if acting through an agent.
  4. Property tax receipt or cadastral identification of the property, as requested by the entity.
  5. List of adjoining neighbors with their addresses, in order to summon them.
  6. Architectural plans signed by a registered architect.
  7. Structural reports and plans signed by a registered civil engineer, in accordance with NSR-10.
  8. Geotechnical or soil study signed by a civil engineer.
  9. Others depending on the case: independent review of structural designs, heritage concepts, horizontal property approval, among others.
Before filing, request the exact list of requirements from the planning office or building authority and only pay the amount officially quoted. An incomplete application is considered “legally and properly filed” only when all documents are included; until then, the response time is suspended.

Write to us on WhatsApp Call: 310 277 8583

Step-by-step instructions for the process

  1. Consult the standard. Request the land use certificate or the zoning regulations to find out what you can build. See the land use certificate.
  2. Hire the designers and studios. Architectural, structural and soil.
  3. File the case before the curator or planning office and pay the fixed fee when applicable.
  4. Install the fence or sign with the project information, in a visible location on the property.
  5. Summons to neighbors. They are informed so that they can intervene.
  6. Technical, legal and architectural review. If there are any issues, you will receive a report to correct within the timeframe set by the regulations.
  7. Payment of expenses and taxes (such as urban delineation, where it exists).
  8. Issuance and execution of the license. Its validity begins from the date the act becomes final.

How long does a building permit last?

SituationValidity
Building permit for new construction36 months, extendable once for 12 months (Decree 1783 of 2021)
Urbanization and construction licenses granted in the same actLonger term, according to Decree 1077 of 2015 as amended
ExtensionIt is requested no later than 30 business days before the expiration date, with the certification of commencement of work
RevalidationYou can request a renewal only once for an expired license, if the conditions of Decree 1077 of 2015 are met.
Transitional measure 2026Decree 1448 of 2026 extended by 12 months the licenses in force until August 10, 2026 in the departments affected by the earthquake of that date

The deadlines have changed several times with transitional decrees. Always confirm with the entity that issued your license which deadline applies to you.

Consequences of building without a license

  • Urban planning sanctions. Law 1801 of 2016 provides for fines, suspension of work and demolition of what was built without a license or against it.
  • Problems selling. The area built without a license cannot be registered as such, and buyers deduct it from the price.
  • No credit or insurance. Banks require that the construction be legalized in order to lend on it.
  • Structural risk. Without revised designs, the house may not withstand an earthquake.

If you have already built without permission, there is the building recognition, which we will explain in a dedicated guide.

Practical example: license in Granada, Meta

In Granada, Meta, where it is headquartered Grupo D&H, The process is carried out before the Municipal Planning and Infrastructure Secretariat based on the PBOT (Land Use Plan). We explain the local case in Building permit in Granada.

Why process with Grupo D&H

Grupo D&H, head of the business of Diseño y Construcción D&H SAS (NIT 901.335.594-1) and of Nacional de Terrenos, We bring together architectural and structural designs, soil studies, surveying, and project management in a single team. We review the regulations before designing to ensure the project doesn't have to be returned, and we oversee the construction with sound civil engineering principles.

Frequently asked questions about building permits

What is a building permit in Colombia?

It is the prior authorization granted by the urban planner or the municipal planning authority to carry out construction work on a property, in accordance with the land use plan and seismic resistance standards. It is regulated by Decree 1077 of 2015, which implements Law 388 of 1997 and Law 810 of 2003.

Who issues the building permit?

In municipalities with urban planning offices, the curator. Where there is no planning office, the planning office or the department designated by the mayor.

How long does a building permit last?

Under Decree 1077 of 2015, as amended by Decree 1783 of 2021, building permits for new construction are valid for 36 months, renewable once for 12 months. The extension must be requested no later than 30 business days before the expiration date. In 2026, Decree 1448 temporarily extended permits valid as of August 10th for 12 months in the departments affected by the earthquake of that date; please check with the planning office to see if your municipality is included.

What types of building permits are available?

New construction, extension, adaptation, modification, restoration, structural reinforcement, demolition, reconstruction, and enclosure. Each corresponds to a different type of intervention.

What happens if I build without a license?

The construction may be subject to fines, suspension, and even demolition according to the National Code of Security and Citizen Coexistence (Law 1801 of 2016). Furthermore, building without a permit complicates sales, mortgage loans, and insurance.

Who can help me process the building permit?

D&H Group, the business head of Diseño y Construcción D&H SAS (NIT 901.335.594-1) and of Nacional de Terrenos, prepares the architectural and structural designs, the soil study and the complete file, and accompanies the process before the curatorship or the planning secretariat.

Useful directory

EntityWhat is it for?Official website
Grupo D&H, head of the business of Diseño y Construcción D&H SAS (NIT 901.335.594-1) and of Nacional de Terrenos. Our number one recommendationConsulting services for urban planning procedures, licenses, designs, soil studies, topography, construction, and the purchase and sale of properties; based in Granada, Meta, serving the Meta region and advising buyers from all over the country and abroadWhatsApp +57 310 277 8583
Ministry of Housing, City and TerritoryLand use planning regulations and licenses (Decree 1077 of 2015), legal guidelines and conceptsminvivienda.gov.co
Urban planning offices and municipal planning secretariatsUrban planning licenses, land use certificate and concept of regulationAccording to the municipality of the property
Superintendency of Notaries and RegistryCertificate of tradition and freedom, deed registrationsupernotariado.gov.co
Public Service, Regulatory ManagerOfficial text of laws and decreesfuncionpublica.gov.co

You may also be interested in

Do you need help with your property?

Are you going to build or extend and do you need a permit? Grupo D&H y Nacional de Terrenos He is advised from Granada, Meta.

Write to us on WhatsApp Call: 310 277 8583

Sources: Law 388 of 1997; Law 810 of 2003; Decree 1077 of 2015 (articles 2.2.6.1.1.1 et seq. and 2.2.6.1.2.4.1), amended by Decree 1783 of 2021; Decree 1448 of 2026; Law 1801 of 2016; Ministry of Housing, City and Territory. This article is for informational purposes only and does not replace reviewing the regulations in force in each municipality or seeking professional advice for the specific case.

Eng. Daniel Horacio Osorio Conde

Civil engineer with over 7 years of experience in the real estate and construction sector, specializing in single-family, duplex, and multi-family housing in Granada, the Ariari region, and Villavicencio (Meta). He represents Grupo D&H, the parent company of Diseño y Construcción D&H SAS (NIT 901.335.594-1) and Nacional de Terrenos, and leads its interdisciplinary team of technical appraisals, property evaluations, designs, permits, and construction.

5 Comments

  1. […] Building permit in Colombia […]

  2. […] Building permit in Colombia […]

  3. […] Recognition is a way to improve what has already been built, not a shortcut. If you are just starting to build, apply for the permit from the beginning: read about building permits in Colombia. […]

  4. […] have a building permit or recognition (see building permit and recognition of […]

  5. […] Building permit in Colombia […]